    What Should Be Included in an Asphalt Paving Bid? A 17-Point Checklist

    Kodey Van HornFounder & Operations Lead, Summit Surface Partners11 min read

    Three paving bids arrive. One is $38,000, one is $52,000, and one is $61,000. The owner picks the low one, and eight months later there is a soft area at the entrance, a puddle that never drains, and a conversation about who owns the repair.

    The bids were never comparable. They described different work. That is the normal condition of paving procurement, not the exception — asphalt is sold by the ton and by the square foot, but it is *delivered* by the assumptions underneath those units.

    This checklist is what a decision-quality asphalt paving bid contains. Use it as a scoring sheet. If a proposal is missing more than three of these, you cannot compare it to anything.

    The 17 Points

    1. Measured quantities, not a lump sum

    Square footage of paving, linear feet of milling and sawcut, tons of asphalt, cubic yards of excavation and imported base. A single lump-sum number tells you nothing about whether the contractor measured your site or eyeballed it from satellite imagery. Quantities are also how you fairly evaluate a change later.

    2. Compacted thickness — stated as compacted, in lifts

    "3 inches of asphalt" is ambiguous. Loose depth compacts down roughly a quarter. The bid should state compacted thickness and how it is placed: a 3-inch compacted mat placed in one lift behaves differently than 4 inches placed in two lifts. If the bid does not say compacted, ask in writing.

    3. Mix design and aggregate size

    The surface mix, its nominal maximum aggregate size, and any binder grade called for. A coarse base mix under a finer surface course is a different product than one generic "hot mix" line. On projects with plans, the bid should name the specified mix rather than a substitute.

    4. Base scope: what is being reused, corrected or imported

    Crushed base depth, whether existing base is being reclaimed, proof-rolled, or replaced, and the cubic yards of imported material assumed. Base is where low bids hide. A bid that assumes your existing base is sound — without saying so — has quietly transferred that risk to you.

    5. Compaction standard and how it is verified

    Density target and the verification method: nuclear gauge, cores, or proof roll observation. On public and institutional work this is usually specified. On private work it is usually absent, which is exactly why private lots fail early.

    6. Subgrade contingency and unit price for soft spots

    Nobody knows what is under a lot until it is opened. A good bid says what happens next: an assumed quantity for undercut and a unit price per cubic yard for anything beyond it. Without that unit price, the discovery becomes a negotiation while your lot is closed.

    7. Drainage: slopes, flow paths, and structures

    Minimum finished slope, where water is intended to go, and whether catch basins, valley gutters, curb, or area drains are being adjusted. Standing water is the single most common post-paving complaint, and it is almost always a scope omission rather than a workmanship failure.

    8. Milling, transitions and tie-ins

    Where the new asphalt meets existing pavement, curb, gutter pan, sidewalk, dock apron or garage slab. Butt joints, sawcut depth, and whether transitions are milled or feathered. Feathered edges at tie-ins are a short-lived detail; they should be an explicit choice, not a surprise.

    9. Structure adjustments

    Manholes, valve boxes, cleanouts, drain grates and monitoring wells raised or lowered to final grade. Count them. Each one is a line item, and each one left out is a bump or a low spot for the next twenty years.

    10. Phasing and access plan

    How the site stays usable: section-by-section closures, night or weekend windows, delivery and dumpster routing, emergency vehicle access, and how tenants or residents are notified. On an occupied property, the access plan is as much of the deliverable as the asphalt.

    11. Traffic control and safety provisions

    Signage, cones, flagging, barricades, pedestrian routing and ADA-accessible paths of travel during construction. Required on public work, frequently skipped on private work, and always a cost that exists whether or not it is in the bid.

    12. Schedule with weather contingency

    Mobilization window, working days, and how weather delays are handled. Asphalt placement is temperature-dependent, so a schedule with no weather language is a schedule that will be renegotiated.

    13. Striping and markings

    Layout, stall count, ADA stalls and access aisles with signage, fire lanes, directional arrows and crosswalks — and the cure time before striping is applied. A newly paved lot without a striping line item is an unfinished lot.

    14. Written exclusions

    This is the most informative section of any paving proposal. Common exclusions: permits, engineering, testing, unsuitable soils, dewatering, utility relocation, landscape restoration, concrete work, striping, and rock excavation. Read exclusions first, then read the price.

    15. Permits, engineering and testing responsibility

    Who pulls permits, who pays fees, whether a survey or engineered grading plan is required, and who pays for independent materials testing. On municipal and institutional projects this is defined in the documents; on private projects it is usually undefined until someone gets a stop-work notice.

    16. Insurance, licensing and bonding

    Certificate of insurance with the limits your property or entity requires, contractor licensing, workers' compensation, and whether payment and performance bonds are included or priced as an alternate. Bonding is a real cost and belongs on the page.

    17. Closeout and the maintenance plan

    As-built quantities, tonnage tickets, testing results if applicable, warranty language in writing, and the recommended preservation schedule — when to first crack seal, when the surface is cured enough for sealcoat, and when to plan the next capital cycle. A paving bid that ends at the last truckload is a bid that ignores nine-tenths of the asset's life.

    How to Score the Bids You Already Have

    Lay the proposals side by side and mark each of the 17 points present, absent, or ambiguous. Then do three things:

    Normalize the scope. Add the missing items to the low bid at the other bidders' stated values. The spread usually collapses, and sometimes it inverts.

    Find the risk transfer. Every absent item is a risk someone is carrying. If the bid doesn't carry it, you do.

    Ask one question per gap, in writing. "Is the compacted thickness 3 inches?" is a five-word email that has settled more paving disputes than any contract clause.

    Red Flags Worth Slowing Down For

    - A bid that arrives without a site visit on anything larger than a driveway.

    - Thickness stated without the word *compacted*.

    - No exclusions section at all — meaning the exclusions still exist, just unwritten.

    - "Overlay" proposed on a lot with widespread alligator cracking, rutting, or standing water. That is a base problem, and an overlay over a failed base fails on the same schedule the base does.

    - A large deposit required before mobilization.

    - Pricing quoted over the phone from an address. Paving cost is driven by access, haul distance, base condition, phasing and traffic control — none of which are visible from a map.

    What Summit Puts in a Proposal

    Our paving proposals are built after a site review and present the decision, not just a number: protect and repair, resurface and extend, or rebuild and correct. Each option carries quantities, assumptions, exclusions, phasing and the expected next-maintenance timing, so the choice can be made on scope rather than on which contractor left the most out.

    Because we also self-perform crack sealing, sealcoating and line striping, the preservation plan is written the same week the paving scope is — not sold to you two summers later.

    Frequently Asked Questions

    Why do paving bids vary so much?

    Because they describe different work. Thickness, base treatment, drainage corrections, structure adjustments, striping, traffic control and exclusions all move the number substantially. Normalize the scope across bids before comparing prices.

    Should I always take the lowest paving bid?

    Only after the scopes match. A low bid that excludes base correction, structure adjustments and striping is not lower — it is smaller. Add the missing scope at market value and re-rank.

    What is the single most important line item?

    Base and subgrade treatment. Surface work can be redone; a failed base means the whole section comes out. It is also the item most often left vague in competitive bids.

    Can I get a paving price without a site visit?

    Not a reliable one. Call for pricing and we will schedule a site walk — square footage, access, haul distance, base condition, phasing and traffic control are what set the number, and none of them are visible from an address.

    Reading this for a specific market?

    Pick your area and the contact details and local links below update — same guide, local context.

    Kalispell, MT

    Highway 93 retail, medical campuses and county facilities. Heaviest freeze-thaw load in the valley, so base repair usually drives the bid more than the mat itself.

    Crews stage out of the Kalispell yard; same-week site walks are typical in season.

    109 Alden Loop Unit A, Kalispell, MT 59901 — our shop and Pitch Black® plant

    (406) 309-SEALFlathead Valley dispatch

    info@summit-surface.com

    Flathead Valley

    Local market notes — Kalispell

    Highway 93 retail, medical campuses and county facilities. Heaviest freeze-thaw load in the valley, so base repair usually drives the bid more than the mat itself.

    When you compare Kalispell bids, line up base repair quantities first — that is where valley numbers diverge most.

    Season window

    Practical mat window runs roughly late April through mid-October, with the best compaction weather in June–September. Overlay work booked after the first hard frost usually slides to spring.

    Permits & approvals

    City of Kalispell and Flathead County right-of-way work needs an approach or encroachment permit; commercial lots off Highway 93 often need an MDT-coordinated traffic plan for the tie-in.

    Scopes we bid most

    • Retail and medical lot overlays with staged phasing to keep entrances open
    • Full-depth base repair at drive aisles and dumpster pads
    • Mill-and-fill at loading areas ahead of sealcoat and striping

    What usually moves the number

    Freeze-thaw is the heaviest in the valley here. Subgrade moisture and failed base — not the mat thickness — is usually what separates a low bid from a bid that lasts.

    Crews stage out of the Kalispell yard; same-week site walks are typical in season.

    Kalispell paving questions

    Answers specific to Kalispell, MT — permitting, scheduling and how each scope gets bid here.

    Free PDF Download

    Asphalt Paving Bid Comparison Checklist (PDF)

    Score three paving bids side by side on the same 17 line items — quantities, thickness, compaction, drainage detailing, traffic control and cleanup — so you can normalize scope before you compare price.

    We use this to route your bid request to the right intake form for Kalispell, MT.

    We'll send occasional pavement tips. No spam. Unsubscribe anytime.

    Get a bid you can actually compare

    We quote against the same 17 line items in this checklist — quantities, thickness, compaction and cleanup all written out. Pick the path that matches your property and we'll scope it the same way. Currently showing Kalispell, MT.

    Commercial parking lots

    Retail centers, offices, medical campuses and industrial yards that need a scoped paving or resurfacing bid.

    Request a commercial paving bid Commercial parking lot paving

    HOA & private roads

    Boards and property managers planning private-road paving, overlays and multi-year reserve funding.

    Start the HOA bid intake HOA & private road paving

    Municipal & institutional

    Cities, counties, schools and districts working through formal bid invites, specs and required documentation.

    Send a bid invitation Municipal & institutional paving
    See all asphalt paving servicesPrefer to talk it through? Call (406) 309-SEAL — call for pricing.

    More Questions Owners and Boards Ask

    How do I compare three paving bids that all say different square footage?

    Measure once yourself, then normalize. Take the most credible quantity, apply it to each bidder's unit rates, and rebuild all three proposals on the same area. Square-footage disagreement usually means one bidder measured curb-to-curb, one measured only the paved area, and one estimated from aerial imagery — the price gap often disappears once the area matches.

    What exclusions should I look for in an asphalt paving proposal?

    The common ones are unsuitable subgrade, rock excavation, dewatering, utility or structure adjustments, engineered testing, permits, striping, landscape restoration, and repairs to areas damaged by delivery traffic. A proposal without a written exclusions list still has exclusions — they are just undocumented and become change orders after the lot is closed.

    Should a paving bid include a unit price for soft subgrade?

    Yes. Ask for an assumed undercut quantity plus a per-cubic-yard unit price for anything beyond it, including haul-off and imported base. That single line converts the worst mid-project surprise into arithmetic instead of a negotiation while your access is closed.

    Do I need testing and inspection on a private commercial lot?

    It is optional on private work and it is the cheapest insurance available. Density verification on the mat and a proof roll on the base cost a fraction of a percent of the project and give you documented evidence if a section fails inside the warranty period.

    What questions should a Kalispell or Whitefish property manager ask before signing?

    Who is the on-site foreman, what is the phasing plan for tenant and guest access, where do delivery trucks and emergency vehicles route during work, what is the weather-delay policy, and when does striping follow the mat. In the Flathead Valley the schedule question matters most — summer paving windows fill early and a bumped date can push work into the shoulder season.

    Is a verbal change order enforceable on a paving project?

    Treat it as if it is not. Require written change orders with quantity, unit price and schedule impact before the work proceeds. On paving, the change is often buried within hours as material goes down, so the paper has to lead the work rather than follow it.

    How long should a paving bid stay valid?

    Liquid asphalt binder pricing moves with crude and with plant season, so many proposals carry a 15 to 45 day validity window and an escalation clause. Ask whether the price is held on signature or on a scheduled start date — those are different commitments.

    What should a paving closeout package contain?

    Weigh tickets, placed quantities, compaction or proof-roll records, photos of subgrade and base before paving, final striping layout, warranty terms with their exclusions, and the recommended date for first crack seal and first sealcoat. That package is what makes the next capital decision defensible.

    Question not answered here? Send the project details or call (406) 309-SEAL — call for pricing.